FRANKLIN COUNTY METROPOLITAN PLANNING ORGANIZATION
POLICY BOARD MEETING
February 13, 2025 – 10:00 am
Franklin County Administrative Building, Room 824
272 North 2nd Street
Chambersburg, PA 17201
Video call link: https://meet.google.com/xdt-jfdf-cte
Or dial: (US) +1 650-966-6674 PIN: 277144421#
I. Welcome and Introduction – Sam Cressler
II. Moment of Silence
III. Pledge of Allegiance
IV. Approval of Meeting Minutes – November 21, 2024 – Action
V. Presentation – Mercersburg-Montgomery-Peters Joint Comprehensive Plan
VI. Business
a. PM 1 Safety Target Letter – Action
b. 2025-2028 TIP Modifications - Action
c. 2025-2028 TIP at a Glance Document – Discussion
d. CVRT Feasibility Study Update - Discussion
VII. Partner Updates
a. Commute PA Update
b. Rabbittransit Update
c. PennDOT Update
d. FHWA Update
e. State/Federal Legislative Update
f. Director’sReport– Quentin Clapper
g. Staff Report – Matthew Romero
VIII. Future Meetings
a. May 15 – Policy Board Meeting 10:00 A.M.
IX. Public Comment
X. Adjournment
“The FCMPO is committed to complying with the nondiscrimination requirements of the Title VI
of the Civil Rights Act of 1964 and related statutes and regulations prohibiting discrimination in
all programs and activities. All locations for meetings open to the public will be accessible to
persons with disabilities. With advance notification, accommodations may be provided for those
with special needs related to language, speech, sight, or hearing. If you have a request for a
special need, wish to file a complaint, or desire additional information, please contact the
Franklin County Planning Department at (717) 261-3855; FAX (717) 264-8667; email:
planning@franklincountypa.gov.”
FRANKLIN COUNTY METROPOLITAN PLANNING ORGANIZATION
POLICY BOARD MEETING
November 21, 2024 – 10:00 am
Franklin County Administrative Building, Room 824
272 North 2nd Street
Chambersburg, PA 17201
-MINUTES-
Members In attendance: David Mackley, Carey Mullins, Nate Walker, Jessee McMath,
Sharon Coffman (Alt.), Sam Cressler, Dean Horst
Staff in Attendance: Quentin Clapper, Matthew Romero, Zak Long
I.Welcome and Introduction – Sam Cressler - Sam Cressler welcomes the board and
thanks everyone in attendance for coming.
II. Moment of Silence
III. Pledge of Allegiance
IV.Approval of Meeting Minutes – August 15, 2024 – Action - Motion to approve August
15th meeting minutes made by David Mackley, Seconded by Dean Horst. Passed
unanimously
V.Business
a.2024-2025 Unified Planning Work Program Budget Amendment - Action - Motion to
approve the budget amendment as presented made by Carey Mullins, Seconded by Nate
Walker. Passed unanimously
b.2025-2027 Draft Unified Planning Work Program – Discussion/Action - Motion to
approve the 2025-2027 UPWP made by Dean Horst , Seconded by David Mackley. Passed
unanimously
c.MPO Bylaw Amendment - Action - Motion to approve bylaw amendment made by
Sharon Coffman, Seconded by Jessee McMath. Passed unanimously
d.2025-2028 TIP Amendments - Action - Motion to approve the TIP amendments
made by Sharon Coffman, Seconded by Dean Horst. Passed unanimouslyDRAFT
e. Establishing 2025 Meeting Schedule – Discussion - Quentin presented the meeting
dates for next year and there were no questions or comments.
f. CVRT Feasibility Study Update - Brian Funkhouser discusses the Cumberland
Valley Rail Trail Feasibility Study progress.
VI. Partner Updates
a. Commute PA Update - Matt Boyer gives an update on CommutePA. They had a
College Month promotion in October. Franklin County placed 3rd in ‘Clash of the
Counties,’ and CommutePA added 201 new people and members. Continuing to move
forward on the congestion management process.
b. Rabbittransit Update - David Juba from RabbitTransit gives an update on
RabbitTransit.
c. PennDOT Update - Sarah McHugh has a construction update on the Anthony
Highway Resurfacing SR997 Section #42. $2.1 million original contract. 4.7 mile
resurfacing in Guilford, Quincy, and Greene Townships. Final Inspection happened and
all the work is now complete.
d. FHWA Update - Kenana from FHWA let us know Ronnique Bishop will be back to
being our contact on Monday.
e. Director’s Report – Quentin Clapper lets the room know he has taken over the role
as Planning Director and that the Senior Planner position is currently in the process of
being filled.
f. Staff Report – Matthew Romero says the HPMS sampling was conducted on
November 8th and will have the report back to PennDot by the beginning of December.
Staff is working on developing the list of annual obligations, as well as developing a TIP
overview document.
VII. Future Meetings - Feb 13th Next meeting
a. January 16th – TAC Meeting 9:30 A.M. (TBD)
b. February 13th – Policy Board Meeting 10 A.M.
VIII. Public Comment - Preston Spahr - President of Mercersburg vibrancy steering
committee - have engaged with HRG as a DCED Matched project to deliver a
Comprehensive Plan for the Mercersburg area covering Montgomery Township, Peters
Township and Mercersburg Borough. The Comp Plan will be delivered to these
municipalities within the next 30 days and that will start the 45 day public review period,
and also a 30 day period for County and School District Review. Preston will return at the
February meeting to present this to the group. DRAFT
IX. Adjournment
Motion to adjourn meeting made by Carey Mullins, Seconded by Dave Mackley.
“The FCMPO is committed to complying with the nondiscrimination requirements of the Title VI
of the Civil Rights Act of 1964 and related statutes and regulations prohibiting discrimination in
all programs and activities. All locations for meetings open to the public will be accessible to
persons with disabilities. With advance notification, accommodations may be provided for those
with special needs related to language, speech, sight, or hearing. If you have a request for a
special need, wish to file a complaint, or desire additional information, please contact the
Franklin County Planning Department at (717) 261-3855; FAX (717) 264-8667; email:
planning@franklincountypa.gov.”
DRAFT
COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF TRANSPORTATION
Office of the Deputy Secretary for Planning
400 North Street | Harrisburg, PA 17120 | 717.787.3154 | www.penndot.pa.gov
October 22, 2024
Dear Planning Partners:
Pursuant to the Code of Federal Regulations (23 CFR § 490) regarding National Performance Management Measures for the Highway Safety Improvement Program
(HSIP), Pennsylvania has established the 2025 targets for the following Safety
Performance Measures:
1)Number of fatalities2)Rate of fatalities per 100 million Vehicle Miles Travelled (VMT)
3)Number of serious injuries
4)Rate of serious injuries per 100 million VMT5)Number of non-motorized fatalities and serious injuries
The Pennsylvania Department of Transportation (PennDOT) is required to establish
these targets by August 31st each year. The 2025 targets found in Table 1 of the enclosure
are based on a data driven trend analysis of the statewide fatality and suspected serious injury numbers (2 percent annual fatality reduction and maintaining level suspected serious injuries).
Metropolitan Planning Organization (MPOs) are required to establish targets within
180 days of PennDOT establishing its targets (by February 27, 2025) either by agreeing to plan and program projects in support of the PennDOT targets, or by establishing their own quantifiable targets. For consistency, PennDOT is requesting Rural Planning Organizations (RPOs) follow the same procedure. Table 2 of the enclosure reflects values
for your MPO/RPO based on the same methodology that was used at the state level.
The MPOs that establish quantifiable fatality rate or serious injury rate targets shall report the VMT estimate used for such targets and the methodology used to develop the estimate. The methodology should be consistent with other Federal reporting
requirements, if applicable. MPOs/RPOs wishing to establish their own quantifiable targets
are requested to coordinate with PennDOT as early as possible, but no later than December 31, 2024.
Planning Partners Page 2 October 22, 2024
A state is determined to have met or made significant progress toward meeting established targets if the outcome in 4 of 5 performance measures is better than the baseline number. For Pennsylvania’s 2023 targets, the Federal Highway Administration (FHWA) will report this determination by March 31, 2025.
Based on preliminary data, we do not expect Pennsylvania to meet our 2023 targets and anticipate will be subject to the provisions of 23 United States Code § 148 (i). This will require the Department to submit an implementation plan that identifies gaps, develops strategies, action steps and best practices, and includes a financial and performance
review of all HSIP funded projects. This plan will be due June 30, 2025. In addition, we will
be required to obligate in Federal Fiscal Year (FFY) 2026 an amount equal to the FFY 2022 HSIP apportionment ($125,848,562).
For more information, please visit the FHWA Safety Performance Management
website at https://safety.fhwa.dot.gov/hsip/spm/.
Your response is requested before February 27, 2025.
Please complete the following:
______________________________________________________________________ Planning Organization Name
Select one of the following options for establishing Safety Performance Measures:
The MPO/RPO agrees to plan and program projects so that they contribute toward the accomplishment of the established PennDOT targets. The MPO/RPO will have the option to establish quantifiable targets of their own each year when new
PennDOT targets are established. Table 2 of the enclosure reflects corresponding
MPO/RPO values.
The MPO/RPO has established quantifiable targets for each performance measure
for our planning area. The targets and methodology used to develop them are
enclosed with this letter. This option will require PennDOT coordination with the Federal Highway Administration to ensure that the targets established are not just aspirational but achievable based on the projects that are programmed on the MPO/RPO’s Transportation Improvement Program. If choosing this option please
notify the Center for Program Development and Management (CPDM) by
December 31, 2024.
Concurrence:
Authorized MPO/RPO Representative Date
☐
☐
MIT
Planning Partners Page 3 October 22, 2024
Should you have any questions, please contact Matthew Crea, Transportation Planning Manager, Center for Program Development and Management, at 717.787.2862
or mcrea@pa.gov.
Sincerely, Sincerely,
Kristin Mulkerin Christine Norris, P.E. Deputy Secretary for Planning Deputy Secretary for Highway Administration
Enclosure
MPO/RPO Target Setting
Enclosure
September 4, 2024
Table 1: Statewide Targets:
Performance Measure
5-year Rolling Averages
TARGET ACTUAL BASELINE
2021-2025 2021-2025 2019-2023
Number of Fatalities 1,192.8 1161.2
Fatality Rate 1.186 1.183
Number of Serious Injuries 4,832.6 4738.6
Serious Injury Rate 4.806 4.828
Number of Non-motorized
Fatalities and Serious Injuries 916.8 833.4
* Future VMT estimated to hold level over next few years
Table 2: Franklin MPO Supporting Values:
Performance Measure
5-year Rolling Averages
TARGET ACTUAL BASELINE
2021-2025 2021-2025 2019-2023
Number of Fatalities 24.4 19.6
Fatality Rate 1.707 1.393
Number of Serious Injuries 75.4 69.4
Serious Injury Rate 5.275 4.933
Number of Non-motorized
Fatalities and Serious Injuries 12.2 9.0
* Future VMT estimated to hold level over next few years
FFY 2025-2028 TIP MODIFICATIONS FORM
Date: 2/3/2025
Page 1 of 1
Item Project Title MPMS Ph Prog Fed Sta.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.
Microtransit Service Before 5307 339
80,000 69,568 10,432 80,000 69,568 10,432 80,000 69,568 10,432 80,000 69,568 10,432
Adjust 5307 339
3,383,872
After 5307 339
3,463,872 69,568 10,432 80,000 69,568 10,432 80,000 69,568 10,432 80,000 69,568 10,432
80,000 69,568 10,432 80,000 69,568 10,432 80,000 69,568 10,432 80,000 69,568 10,432
3,383,872 0 0 0 0 0 0 0 0 0 0 0 03,463,872 69,568 10,432 80,000 69,568 10,432 80,000 69,568 10,432 80,000 69,568 10,432
SRTA, on behalf of CPTA is requesting a
TIP Administrative Modification to add the
following unused, prior year apportioned
funds to project #121378 Microtransit
Service for FFY 2025:
The Section 5307 operating apportionment
funds available:
FFY 2021 = $687,114
FFY 2022 = $886,994
FFY 2023 = $905,913
FFY 2024 = $903,851
Total = $3,383,872
SRTA is currently in the process of
preparing a federal grant that will utilize the
older funds. The remaining amount will be
used for future grant purposes.
121328 CON
Informed Coordinating Committee: 2/13/25
Informed Technical Committee: N/A
Amendment - Transit Funds
Remarks
FFY 2028FFY 2025 FFY 2026 FFY 2027
Franklin
After FFY Totals
Before FFY Totals
Program Summary - Net Changes Adjustments
1
(S:\planning\mpo\Harrisburg\meetings\2010 meetings\HATS 2011 tip revisions June 10 to Sept 9 2011 meeting.xls)
FFY 2025-2028 TIP MODIFICATIONS FORM
***NOTE: Strictly TYP modifications exist but are not being included in the interest of brevity. They can be produced upon request.***
Item Project Title MPMS Ph Prog Fed Sta.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.
Highway Reserve Before STP 581 1,297,799 2,207,018 1,151,562 1,279,926
Before NHPP
Adjust STP 581 642,416 -920,542
Adjust NHPP
After STP 581 642,416 377,257 2,207,018 1,151,562 1,279,926
Franklin After NHPP
Swamp Fox Rd over I-81 Before BRIP 562,000 402,280
914/003 Adjust BRIP 402,280 -402,280
Franklin After BRIP 402,280 562,000
Hykes Rd over I-81 Before BOF 802,889 12,584 796,000 195,731
Before BRIP 405,874 1,562,000 1,000,000 1,159,720
Before STP 642,416
3014/013 Adjust BOF -802,889 930,637
Adjust BRIP -405,874 -402,280 402,280
Adjust STP -642,416 920,542
After BOF 12,584 796,000 1,126,368
After BRIP 1,159,720 1,000,000 1,562,000
Franklin After STP 920,542
Franklin Bridge Reserve Before BOF 185 39,000 930,637
Before BRIP
Adjust BOF 185 802,889 -930,637
Adjust BRIP 405,874
After BOF 185 39,000 802,889
Franklin After BRIP 405,874
Newburg Road over Paxtons
Run Before 185 405,026
Before 581 541,221
641/037 Adjust 185 -300,000 300,000
Adjust 581
After 185 105,026 300,000
Franklin After 581 541,221
Rolling Rd ov Tributary to
Back Ck Before 185 615,000
3028/007 Adjust 185 300,000 -300,000
Franklin After 185 300,000 315,000
Rockdale Rd ov Trib to Back
Cr Before 185 394,000 383,162
Before
3017/035 Adjust 185 -394,000 394,000
Adjust 581
After 185 777,162
Franklin After 581
I-81 New Interchange (Exit
12)Before NHPP 185 780,780 342,342 588,780 1,338,000
Before sNHPP 581 3,744,048 10,000,000 3,978,170 10,000,000 1,588,468
81/075 Adjust NHPP 185 394,000
Adjust sNHPP 581 -394,000
After NHPP 185 780,780 736,342 588,780 1,338,000
Franklin After sNHPP 581 3,744,048 10,000,000 3,584,170 10,000,000 1,588,468
Cashflowing the CON phase of Newburg Road over Paxtons Run
from FFY 2027 to FFY 2028 for $300,000 to better utilize current
available funds. This project consists of a bridge improvement
(replacement, rehabilitation or preservation) on PA 641 (Newburg
Road) over Paxtons Run in Lurgans Township, Franklin County. The
estimated let date of this project is 11/5/2026.
Cashflowing the CON phase of Rockdale Rd ov Trib to Back Cr
from FFY 2026 to FFY 2027 for $394,000 to better align with the
current estimated let date. This project may consist of a bridge
improvement (replacement, rehabilitation or preservation) on SR
3017 (Rockdale Road) over tributary to Back Creek in Peters
Township, Franklin County. The estimated let date of this project is
11/05/2026.
1 87805 CON
2 117156 CON
3 117143 CON
4 87804 CON
This is a reserve line item.
Cashflowing the CON phase of Rolling Rd ov Tributary to Back Ck
from FFY 2028 to FFY 2027 for $300,000 to better align with the
current estimated let date. This project consists of a bridge
improvement (replacement, rehabilitation or preservation) on SR
3028 (Rolling Road) over tributary to Back Creek in Saint Thomas
Township, Franklin County. The estimated let date of this project is
11/5/2026.
Informed Coordinating Committee: 2/13/25
Informed Technical Committee: N/A
FFY 2029 - FFY 2036
Remarks
Franklin MPO
Administrative Modification - Highway Funds FFY 2026FFY 2025 FFY 2027 FFY 2028
This is a reserve line item.
Cashflowing the CON phase of Swamp Fox Rd over I-81 for
$402,280 from FFY 2029 to FFY 2027 to better align with the
current estimated let date. This project may consist of a bridge
improvement (replacement, rehabilitation or preservation) on PA
914 (Swamp Fox Road) over I-81 in Guilford Township, Franklin
County. The estimated let date of this project is 11/05/2026.
Cashflowing the CON phase of Hykes Rd over I-81 for $1,851,179
from FFY 2026 to FFY 2027 and FFY 2029. This project may
consist of a bridge improvement (replacement, rehabilitation or
preservation) on SR 3014 (Hykes Road) over I-81 in Antrim
Township, Franklin County. The estimated let date of this project is
11/05/2026.
5 117157 CON
7 116962 CON
CON
Cashflowing the CON phase of I-81 New Interchange (Exit 12) from
FFY 2026 to FFY 2027 for $394,000 to better utilize current
available funds. This project consists of a new interchange (Exit 12)
on I-81 at Guilford Springs Road overpass, Franklin County.
Guilford Springs Road is a township road and the bridge over I-81 is
a state-owned bridge. The estimated let date of this project is
12/11/2025.
6 117141 CON
8 93055
FFY 2025-2028 TIP MODIFICATIONS FORM
***NOTE: Strictly TYP modifications exist but are not being included in the interest of brevity. They can be produced upon request.***
Item Project Title MPMS Ph Prog Fed Sta.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.
FFY 2029 - FFY 2036
Remarks
Administrative Modification - Highway Funds FFY 2026FFY 2025 FFY 2027 FFY 2028
Fort Loudon Rd ov Buck Run Before 185 380,987 1,105,161
Before
75/013 Adjust 185 513,872 -1,105,161
Adjust 581 591,289
After 185 513,872 380,987
Franklin After 581 591,289
I-81 New Interchange (Exit
12)Before NHPP 185 780,780 736,342 588,780 1,338,000 185,374
Before STP 581 3,744,048 3,584,170 1,588,468
Before BRIP
Before sNHPP 10,000,000 10,000,000
Adjust NHPP 185 -513,872 1,105,161
81/075 Adjust STP 581 -591,289
Adjust BOF
Adjust sNHPP
After NHPP 185 780,780 222,470 588,780 1,338,000 1,290,535
After STP 581 3,744,048 2,992,881 1,588,468
After BRIP
Franklin After sNHPP 10,000,000 10,000,000
PA997 & SR2015
Intersection Before HSIP
277,486
997/037 Adjust HSIP
-277,486
York After HSIP
HSIP Line Item Before HSIP
2,912,272
Adjust HSIP
-2,093,000
York After HSIP
819,272
PA997 & SR2015
Intersection Before HSIP 993,514 1,301,000 735,000
Before STP 1,526,486 1,219,000 700,000 1,526,778
997/037 Adjust HSIP 277,486 2,093,000
Adjust STP -800,000 -600,000 -485,243 -485,243
After HSIP 1,271,000 1,301,000 735,000 2,093,000
York After STP 726,486 619,000 214,757 1,041,535
Highway Reserve Before STP 581 580,238 642,416 357,497 1,151,562
Before NHPP
Adjust STP 581 800,000 600,000 485,243 485,243
Adjust NHPP
After STP 581 1,380,238 1,242,416 485,243 842,740 1,151,562
York After NHPP
Cashflowing the CON phase of Fort Loudon Rd ov Buck Run in
FFY 2029 and FFY 2030 to FFY 2026 and FFY 2027 for
$1,105,161 to better align with the current estimated let date. This
project may consist of a bridge improvement (replacement,
rehabilitation or preservation) on PA 75 (Fort Loudon Road) over
Buck Run in Peters Township, Franklin County. The estimated let
date of this project is 9/17/2026.
Cashflowing the CON phase of I-81 New Interchange (Exit 12) from
FFY 2026 and FFY 2027 to FFY 2029 and FFY 2030 for
$1,105,161 to better utilize current available funds. This project
consists of a new interchange (Exit 12) on I-81 at Guilford Springs
Road overpass, Franklin County. Guilford Springs Road is a
township road and the bridge over I-81 is a state-owned bridge. The
estimated let date of this project is 12/11/2025.
11 106709 FD
Removing the FD phase of PA997 & SR2015 Intersection
for $277,486 in FFY 2025 because this phase was previously
obligated off of the 2023 TIP. This project consists of
installing two roundabouts at the intersection of PA997 and
SR2015 (Tomstown Road) and the intersection of PA997
and Washington Township Boulevard in Washington
Township, Franklin County. This project has an estimated let
date of 1/16/2025.
This is a reserve line item.
13 106709 CON
14 87805 CON
Cashflowing the CON phase of PA997 & SR2015
Intersection from FFY 2025- FFY2028 to FFY FFY 2030-
FFY 2032 for $2,370,486 to better utilize current available
funds. This project consists of installing two roundabouts at
the intersection of PA997 and SR2015 (Tomstown Road)
and the intersection of PA 997 and Washington Township
Boulevard in Washington Township, Franklin County. This
project has an estimated let date of 1/16/2025.
This is a reserve line item.
9 78690 CON
10 93055 CON
12 87816 CON
FFY 2025-2028 TIP MODIFICATIONS FORM
***NOTE: Strictly TYP modifications exist but are not being included in the interest of brevity. They can be produced upon request.***
Item Project Title MPMS Ph Prog Fed Sta.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.
FFY 2029 - FFY 2036
Remarks
Administrative Modification - Highway Funds FFY 2026FFY 2025 FFY 2027 FFY 2028
Lincoln Way Intersection
Safety Imp Before
30/150 Adjust STP
538,401
Franklin After STP
538,401
Highway Reserve Before STP 581
1,380,238 1,242,416 485,243 842,740 1,151,562
Before NHPP
Adjust STP 581
-538,401
Adjust NHPP
After STP 581
841,837 1,242,416 485,243 842,740 1,151,562
Franklin After NHPP
I-81 New Interchange (Exit
12)Before
81/075 Adjust STP
134,036
Franklin After STP
134,036
Highway Reserve Before STP 581
841,837 1,242,416 485,243 842,740 1,151,562 842,740 1,151,562
Before NHPP
Adjust STP 581
-134,036
Adjust NHPP
After STP 581 707,801 1,242,416 485,243 842,740 1,151,562 842,740 1,151,562
Franklin After NHPP
This is a reserve line item.
Increasing the PE phase of Lincoln Way Intersection Safety
Imp for $538,401 in FFY 2025 for completing the alternative
analysis process and then progressing the Preliminary
Engineering phase which includes project management and
environmental studies. This project may consist of safety
improvements, potentially including an intersection
realignment with lane widening or converting the intersection
to a roundabout at the intersection of US 30 (Lincoln Way)
and SR 4013 (Sollenberger Road) in Hamilton Township and
Adding/increasing the FD phase of I-81 New Interchange
(Exit 12) for $134,036 in FFY 2025 for Alternate Pavement
design modification per CO, on going utility coordination and
development including now incorporating utility plans/items
not originally scoped, GP-11 permit determined during final
design for culvert repairs. This project consists of a new
interchange (Exit 12) on I-81 at Guilford Springs Road
overpass, Franklin County. Guilford Springs Road is a
township road and the bridge over I-81 is a state-owned
bridge. The estimated let date for this project is 12/11/2025.
17 93055 FD
16 87805 CON
This is a reserve line item.
15 114555 PE
18 87805 CON
FFY 2025-2028 TIP MODIFICATIONS FORM
***NOTE: Strictly TYP modifications exist but are not being included in the interest of brevity. They can be produced upon request.***
Item Project Title MPMS Ph Prog Fed Sta.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.
FFY 2029 - FFY 2036
Remarks
Administrative Modification - Highway Funds FFY 2026FFY 2025 FFY 2027 FFY 2028
Fort Loudon Rd Resurf 2 Before 581
75/014 Adjust 581 94,535
Franklin After 581 94,535
Fort Loudon Rd Resurf 2 Before 581
75/014 Adjust 581 25,000
Franklin After 581 25,000
Swamp Fox Rd over I-81 Before
914/003 Adjust BRIP 40,000
Franklin After BRIP 40,000
Swamp Fox Rd over I-81 Before
914/003 Adjust BRIP 20,000
Franklin After BRIP 20,000
I-81 New Interchange (Exit
12)Before NHPP 185 878,780 738,974
Before BRIP 581 383,050 2,558,791
Before STP 933,827
Adjust NHPP 185
Adjust BRIP 581 -60,000 -329,535
Adjust STP 389,535
After NHPP 185 878,780 738,974
Franklin After BRIP 581 323,050 2,229,256
Franklin After STP 1,323,362
Highway Reserve Before STP 581 707,801 1,242,416 485,243 842,740 1,151,562
Before NHPP
Adjust STP 581 -389,535 210,000
Adjust NHPP
After STP 581 318,266 210,000 1,242,416 485,243 842,740 1,151,562
Franklin After NHPP
UTL
Cashflowing the UTL phase of I-81 New Interchange (Exit
12) for $389,535 in FFY 2025 to better utilize current
available funds. This project consists of a new interchange
(Exit 12) on I-81 at Guilford Springs Road overpass,
Franklin County. Guilford Springs Road is a township road
and the bridge over I-81 is a state-owned bridge. The
estimated let date of this project is 12/11/2025.
UTL
Adding the UTL phase of Fort Loudon Rd Resurf 2 for
$94,545 in FFY 2025 to the current estimate. This project
may consist of resurfacing on PA-75 from Licking Creek to
PA-16 in Montgomery Township and Mercersburg Borough.
The estimated let date of this project is 6/05/20205.
22 117156 ROW
CON
This is a reserve line item.
23 93055
Adding the ROW phase of Swamp Fox Rd over I-81 for
$20,000 in FFY 2025 to the current estimate. This project
may consist of a bridge improvement (replacement,
rehabilitation or preservation) on PA 914 (Swamp Fox Road)
over I-81 in Guilford Township, Franklin County. The
estimated let date of this project is 11/5/2026.
19
24 87805
21 117156 UTL
20 90995 ROW
Adding the UTL phase of Swamp Fox Rd over I-81 for
$40,000 in FFY 2025 to the current estimate. This project
may consist of a bridge improvement (replacement,
rehabilitation or preservation) on PA 914 (Swamp Fox Road)
over I-81 in Guilford Township, Franklin County. The
estimated let date of this project is 11/5/2026.
Adding the ROW phase of Fort Loudon Rd Resurf 2 for
$25,000 in FFY 2025 to the current estimate. This project
may consist of resurfacing on PA-75 from Licking Creek to
PA-16 in Montgomery Township and Mercersburg Borough.
The estimated let date of this project is 6/05/20205.
90995
FFY 2025-2028 TIP MODIFICATIONS FORM
***NOTE: Strictly TYP modifications exist but are not being included in the interest of brevity. They can be produced upon request.***
Item Project Title MPMS Ph Prog Fed Sta.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.
FFY 2029 - FFY 2036
Remarks
Administrative Modification - Highway Funds FFY 2026FFY 2025 FFY 2027 FFY 2028
Lincoln Way Intersection
Safety Imp Before
30/150 Adjust STP
292,000
Franklin After STP
292,000
Lincoln Way Intersection
Safety Imp Before
30/150 Adjust STP
54,000
Franklin After STP
54,000
Lincoln Way Intersection
Safety Imp Before
30/150 Adjust STP
250,000
Franklin After STP
250,000
Highway Reserve Before STP 581 318,266 210,000 1,242,416 485,243 842,740 1,151,562
Before NHPP
Adjust STP 581 -596,000
Adjust NHPP
After STP 581 318,266 210,000 646,416 485,243 842,740 1,151,562
Franklin After NHPP
Hykes Rd over I-81 Before
3014/013 Adjust BOF 50,000
Franklin After BOF
50,000
Franklin Bridge Reserve Before BOF 39,000 802,889
Before BRIP 47,731 405,874
Adjust BOF -50,000
Adjust BRIP
After BOF 39,000 752,889
Franklin After BRIP 47,731 405,874
25 114555 FD
26 114555
This is a reserve line item.
This is a reserve line item.
Adding the UTL phase of Hykes Rd over I-81 for $50,000 in
FFY 2026 to the current estimate. This project may consist
of a bridge improvement (replacement, rehabilitation or
preservation) on SR 3014 (Hykes Road) over I-81 in Antrim
Township, Franklin County. The estimated let date of this
project is 11/5/2026.
UTL
Adding the FD phase of Lincoln Way Intersection Safety Imp
for $292,000 in FFY 2026 to the current estimate. This
project may consist of safety improvements, potentially
including an intersection realignment with lane widening or
converting the intersection to a roundabout at the intersection
of US 30 (Lincoln Way) and SR 4013 (Sollenberger Road)
in Hamilton Township and Chambersburg Borough, Franklin
County. The estimated let date of this project is 3/12/2026.
Adding the UTL phase of Lincoln Way Intersection Safety
Imp for $54,000 in FFY 2026 to the current estimate. This
project may consist of safety improvements, potentially
including an intersection realignment with lane widening or
converting the intersection to a roundabout at the intersection
of US 30 (Lincoln Way) and SR 4013 (Sollenberger Road)
in Hamilton Township and Chambersburg Borough, Franklin
County. The estimated let date of this project is 3/12/2026.
27 114555 ROW
Adding the ROW phase of Lincoln Way Intersection Safety
Imp for $250,000 in FFY 2026 to the current estimate. This
project may consist of safety improvements, potentially
including an intersection realignment with lane widening or
converting the intersection to a roundabout at the intersection
of US 30 (Lincoln Way) and SR 4013 (Sollenberger Road)
in Hamilton Township and Chambersburg Borough, Franklin
County. The estimated let date of this project is 3/12/2026.
CON
29 117143 UTL
28 87805 CON
30 87804
FFY 2025-2028 TIP MODIFICATIONS FORM
***NOTE: Strictly TYP modifications exist but are not being included in the interest of brevity. They can be produced upon request.***
Item Project Title MPMS Ph Prog Fed Sta.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.
FFY 2029 - FFY 2036
Remarks
Administrative Modification - Highway Funds FFY 2026FFY 2025 FFY 2027 FFY 2028
Chambersburg Signals Imp
Phase 2 Before
11/125 Adjust CRP 169,940
Franklin After CRP 169,940Chambersburg Signals Imp
Phase 2 Before CRP 526,000
Before CRPU 135,000 18,770
11/125 Adjust CRP -169,940 169,940
Adjust CRPU
After CRP 356,060 169,940
Franklin After CRPU 135,000 18,770
Carbon Reduction Program
(CRP) Chambersburg RSL Before CRP 540,000 540,000 540,000
Adjust CRP -169,940
Franklin After CRP 370,060 540,000 540,000
Fort Loudon Rd Resurf 2 Before
75/014 Adjust 581
39,155
Franklin After 581
39,155
Highway Reserve Before STP 581
318,266 210,000 646,416 842,740 1,151,562
Adjust STP 581
-39,155
Franklin After STP 581 318,266 170,845 646,416 842,740 1,151,562
Adding the FD phase of Chambersburg Signals Imp Phase 2
for $169,940 in FFY 2025 to the current estimate. This
project consists of upgrades of signals and interconnect
improvements at 62 signalized intersections in Chambersburg
Borough, Guilford and Hamilton Townships, Franklin
County. The estimated let date of this project is 5/22/2025.
Cashflowing the CON phase of Chambersburg Signals Imp
Phase 2 for $169,940 from FFY 2025 to FFY 2026 to better
align with the current estimated let date. This project consists
of upgrades of signals and interconnect improvements at 62
signalized intersections in Chambersburg Borough, Guilford
and Hamilton Townships, Franklin County. The estimated let
date of this project is 5/22/2025.
This is a reserve line item.
35 87805 CON
This is a reserve line item.
34 90995 PE
Adding the PE phase of Fort Loudon Rd Resurf 2 for
$39,155 in FFY 2025 for additional subsurface utility
engineering. This project may consist of resurfacing on PA-
75 from Licking Creek to PA-16 in Montgomery Township
and Mercersburg Borough. The estimated let date of this
project is 6/5/2025.
33 119286 CON
31 116146 FD
32 116146 CON
FFY 2025-2028 TIP MODIFICATIONS FORM
***NOTE: Strictly TYP modifications exist but are not being included in the interest of brevity. They can be produced upon request.***
Item Project Title MPMS Ph Prog Fed Sta.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.
FFY 2029 - FFY 2036
Remarks
Administrative Modification - Highway Funds FFY 2026FFY 2025 FFY 2027 FFY 2028
PA 997 & SR 2015
Intersection Before HSIP
1,271,000 1,301,000 735,000 2,093,000
Before STP
726,486 619,000 214,757 1,041,535
997/037 Adjust HSIP
566,000 449,383 -2,093,000
Adjust STP
After HSIP
1,271,000 1,301,000 1,301,000 449,383
Franklin After STP
726,486 619,000 214,757 1,041,535
Lincoln Way Intersection
Safety Imp Before HSIP
566,000 1,301,000 990,728
30/150 Adjust HSIP
-566,000 -449,383 1,015,383
Franklin After HSIP
851,617
HSIP Line Item Before HSIP 819,272
Adjust HSIP 1,077,617
Franklin After HSIP 1,896,889
Decreasing the CON phase of PA 997 & SR 2015
Intersection for $1,077,617 in FFY 2031/2032 to the low bid
amount. This project consists of installing two roundabouts
at the intersection of PA997 and SR2015 (Tomstown Road)
and the intersection of PA997 and Washington Township
Boulevard in Washington Township, Franklin County. This
project was let on Jan. 16, 2025.
Cashflowing the CON phase of Lincoln Way Intersection
Safety Imp for $1,015,383 from FFY 2027/2028 to FFY
2030/2031. This is to better align with the current estimated
let date. This project may consist of safety improvements,
potentially including an intersection realignment with lane
widening or converting the intersection to a roundabout at the
intersection of US 30 (Lincoln Way) and SR 4013
(Sollenberger Road) in Hamilton Township and
Chambersburg Borough, Franklin County. This project has a
current estimated let date of Feb. 17, 2028.
This is a reserve line item.
36 106709 CON
37 114555 CON
38 87816 CON
FFY 2025-2028 TIP MODIFICATIONS FORM
***NOTE: Strictly TYP modifications exist but are not being included in the interest of brevity. They can be produced upon request.***
Item Project Title MPMS Ph Prog Fed Sta.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.
FFY 2029 - FFY 2036
Remarks
Administrative Modification - Highway Funds FFY 2026FFY 2025 FFY 2027 FFY 2028
I-81 New Interchange (Exit
12)Before NHPP 581 780,780 3,744,048 588,780 2,992,881 1,338,000 1,588,468
Before sNHPP 185 222,470 10,000,000 10,000,000
Before BRIP
Before STP 5,649,974
Adjust NHPP 581 -2,992,881 -1,588,468
81/075 Adjust sNHPP 185
Adjust BRIP
Adjust STP -5,205,824
After NHPP 581 780,780 3,744,048 588,780 1,338,000
After sNHPP 185 222,470 10,000,000 10,000,000
After BRIPFranklinAfterSTP 444,150
Stone Bridge Road Bridge Before 185
1,900,155
4006/007 Adjust BOF 185
5,940,000 -1,900,155
Franklin After BOF 5,940,000
Stone Bridge Road Bridge Before BOF
275,000
4006/007 Adjust BOF -275,000 300,000
Franklin After BOF 300,000
Stone Bridge Road Bridge Before BOF
4006/007 Adjust BOF 15,000
Franklin After BOF 15,000
Stone Bridge Road Bridge Before BOF
4006/007 Adjust BOF 25,000
Franklin After BOF 25,000
Sollenberger Rd Resurf Before 581 1,972,000
4013/021 Adjust 581 -1,972,000
Franklin After
Franklin Bridge Reserve Before BOF 185 39,000 752,889 7,942,532 4,903,845
Before BRIP 47,731 405,874
Adjust BOF 185 275,000 -340,000 -5,940,000 1,900,155
Adjust BRIP
After BOF 185 314,000 412,889 2,002,532 6,804,000
Franklin After BRIP 47,731 405,874
Highway Reserve Before STP 581 318,266 170,845 646,416 485,243 842,740 1,151,562 18,000 1,575,700
Before NHPP
Adjust STP 581 2,992,881 1,588,468 5,204,824 1,972,000
Adjust NHPP
After STP 581 318,266 170,845 646,416 485,243 2,992,881 842,740 2,740,030 5,222,824 3,547,700
Franklin After NHPP
12,604,003 3,888,610 0 18,464,727 12,927,298 0 40,555,695 11,884,630 0 48,402,268 14,973,887 0 21,044,614 16,985,995 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
12,604,003 3,888,610 0 18,464,727 12,927,298 0 40,555,695 11,884,630 0 48,402,268 14,973,887 0 19,037,503 16,985,995 0After FFY Totals
Before FFY Totals
Program Summary - Net Changes Adjustments
39
UTL
43 63174 ROW
93055 CON
40
Decreasing the CON phase of I-81 New Interchange (Exit
12) $9,787,173 in FFY 2027-2031 due to receiving
additional spike funds for the project. This project consists of
a new interchange (Exit 12) on I-81 at Guilford Springs
Road overpass, Franklin County. Guilford Springs Road is a
township road and the bridge over I-81 is a state-owned
bridge. This project has a current estimated let date of Dec.
11, 2025.
Increasing and changing the funding type of the CON phase
of I-81 Stone Bridge Road Bridge $4,039,845 in FFY 2030-
2033 to the current estimated cost. This project may consist
of a bridge improvement (replacement, rehabilitation or
preservation) on SR 4006 (Stone Bridge Road) over West
Branch of Conococheague Creek in Metal Township,
Franklin County. This project has a current estimated let date
of June 6, 2030.
Increasing and cashflowing the FD phase of I-81 Stone
Bridge Road Bridge $25,000 from FFY 2025 to FFY 2026
to the current estimated cost. This project may consist of a
bridge improvement (replacement, rehabilitation or
preservation) on SR 4006 (Stone Bridge Road) over West
Branch of Conococheague Creek in Metal Township,
Franklin County. This project has a current estimated let date
of June 6, 2030.
Adding the UTL phase of I-81 Stone Bridge Road Bridge
$15,000 in FFY 2026 to the current estimated cost. This
project may consist of a bridge improvement (replacement,
rehabilitation or preservation) on SR 4006 (Stone Bridge
Road) over West Branch of Conococheague Creek in Metal
Township, Franklin County. This project has a current
estimated let date of June 6, 2030.
Adding the ROW phase of I-81 Stone Bridge Road Bridge
$25,000 in FFY 2026 to the current estimated cost. This
project may consist of a bridge improvement (replacement,
rehabilitation or preservation) on SR 4006 (Stone Bridge
Road) over West Branch of Conococheague Creek in Metal
Township, Franklin County. This project has a current
estimated let date of June 6, 2030.
Removing the CON phase of Sollenberger Rd Resurf for
$1,972,000 in FFY 2030/2031. This project will be done by
PennDOT Maintenance Forces. This project consists of a
Resurfacing on Sollenberger Rd (SR 4013) from Lincoln
Hwy (US 30) to Edenville Rd (SR 4009) in Hamilton
Township, Franklin County.
This is a reserve line item.
This is a reserve line item.
44 113285 CON
45 87804 CON
46 87805 CON
63174 CON
41 63174 FD
42 63174
FISCAL CONSTRAINT CHART
FFY 2025-2028 TIP Highway/Bridge
Project Title MPMS Phase Amts Fed State Federal State Loc/Oth Federal State Loc/Oth Federal State Loc/Oth Federal State Loc/Oth
PROTECT Reserve Before PRTCT 57,201,144 56,517,200 62,639,000 62,639,000
/Adjust PRTCT (886,086)
Central Office After PRTCT 56,315,058 56,517,200 62,639,000 62,639,000
SR 16 Retaining Wall Before
16/056 Adjust PRTCT 106,980
Franklin After PRTCT 106,980
SR 16 Retaining Wall Before
16/056 Adjust PRTCT 15,217
Franklin After PRTCT 15,217
SR 16 Retaining Wall Before
16/056 Adjust PRTCT 13,889
Franklin After PRTCT 13,889
SR 16 Retaining Wall Before
16/056 Adjust PRTCT 750,000
Franklin After PRTCT 750,000
$57,201,144 $0 $0 $56,517,200 $0 $0 $62,639,000 $0 $0 $62,639,000 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$57,201,144 $0 $0 $56,517,200 $0 $0 $62,639,000 $0 $0 $62,639,000 $0 $0
Actions do not affect air quality
conformity.
Remarks
Administrative Action (MA ID: 137912)
D8-0 Statewide & Franklin TIPs Fund Type FFY 2025 FFY 2026 FFY 2027 FFY 2028
NOTES
Before Totals
Adjustment Totals
After Totals
118322 CON
PROTECT Reserve line item used as
source of funds to maintain fiscal
constraint.
121390 CON Adding 2023 PROTECT project to the
current TIP.
Adding 2023 PROTECT project to the
current TIP. 121390 UTL
121390 FD Adding 2023 PROTECT project to the
current TIP.
121390 ROW Adding 2023 PROTECT project to the
current TIP.
\\pdkbdata2k01\data\Planning\MPO-RPO\Franklin County\Franklin MPO Meetings\2025 Meetings\January 2025 (Actually February now that bylaws moved tech to adhoc)\Statewide\Copy of FCC72 - D8 PRTCT MPMS 121390 121438 121409 Add - mpl
FISCAL CONSTRAINT CHART
FFY 2025-2028 TIP Highway/Bridge
Project Title MPMS Phase Amts Fed State Federal State Loc/Oth Federal State Loc/Oth Federal State Loc/Oth Federal State Loc/Oth
TAP Oversight & Mngmt Before TAP 88,631 1,050,000
/Adjust TAP (298)
Central Office After TAP 88,333 1,050,000
Waynesboro Ped Safety Project Before TAP 28,823
16/TAP Adjust TAP 298
Franklin After TAP 29,121
$117,454 $0 $0 $1,050,000 $0 $0 $0 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$117,454 $0 $0 $1,050,000 $0 $0 $0 $0 $0 $0 $0 $0
Remarks
Administrative Action (MA ID: 138523)
STWD - Franklin Fund Type FFY 2025 FFY 2026 FFY 2027 FFY 2028
NOTES
104412 PE Funding source
111394 CON Increase to cover AUC
Before Totals
Adjustment Totals
After Totals
Actions do not affect air quality
conformity.
\\pdkbdata2k01\data\Planning\MPO-RPO\Franklin County\Franklin MPO Meetings\2025 Meetings\January 2025 (Actually February now that bylaws moved tech to adhoc)\Statewide\FCC - TAP - D8 - MPMS 111394 - CON Increase - jmc
FISCAL CONSTRAINT CHART
FFY 2025-2028 TIP Highway/Bridge
Project Title MPMS Phase Amts Fed State Federal State Loc/Oth Federal State Loc/Oth Federal State Loc/Oth Federal State Loc/Oth
I-81 Maryland to Mile 6 Before NHPP 12,554,777 3,399,037
81/099 Adjust NHPP 2,746,186 2,204,490
Franklin After NHPP 15,300,963 5,603,527
Interstate Contingency Before NHPP 3,710,913 15,415,873 9,322,840
/Adjust NHPP (2,746,186)(2,204,490)
Central Office After NHPP 964,727 13,211,383 9,322,840
$16,265,690 $0 $0 $18,814,910 $0 $0 $9,322,840 $0 $0 $0 $0 $0
$0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 $0
$16,265,690 $0 $0 $18,814,910 $0 $0 $9,322,840 $0 $0 $0 $0 $0
Remarks
Administrative Action (MA ID:138243 )Fund Type FFY 2025 FFY 2026 FFY 2027 FFY 2028
NOTES
92006 CON
Construction cost increase. Includes
$2,746,186 programmatic adjustment
from 2023 program. CPDM item
submitted on 1/7/2025.
75891 CON Line Item used to maintain fiscal
constraint.
Before Totals
Adjustment Totals
After Totals
Actions do not affect air quality
conformity.
\\pdkbdata2k01\data\Planning\MPO-RPO\Franklin County\Franklin MPO Meetings\2025 Meetings\January 2025 (Actually February now that bylaws moved tech to adhoc)\Statewide\FCC-D8 NHPP MPMS 92006 increase -mjc
1
Franklin MPO Meeting Project Updates
February 2025 Meeting
Project Description Anthony Highway Resurfacing
ECMS # 113270
SR-Section 997-042
Contractor New Enterprise Stone & Lime Co., Inc.
Original Contract Value $2,101,330.99
NTP date 4/11/2024
Original Completion Date 10/25/2024
Project Scope
SR 0997-042 is a 4.76-mile resurfacing project consisting of base repair,
overlay with some variable depth milling, minor drainage updates, guiderail
updates, and other miscellaneous work, all as indicated on the approved
drawing included in the Bid Package for STATE ROUTE 0997, SECTION 042,
FRANKLIN COUNTY, GUILFORD, QUINCY, & GREENE TOWNSHIPS, from
Segment 0230 Offset 0570 (Paving notch north of West Branch Antietam Creek) to Segment 0320 Offset 3451 (Intersection of SR 0997 and SR 0030), for an overall project length of 25,091.00 linear feet (4.752 miles).
Project Update
Final inspection held on October 9, 2024. All physical work is complete. One
additional corrugated metal cross pipe was replaced with an elliptical
concrete pipe. Project added a three-day detour to replace the two cross
pipes. Project had various other quantity overruns most notably 25mm base
replacement and stone shoulder backup.
Project Update Complete
Project Description West King Street Bridge
ECMS # 19304
SR-Section 11-095
Contractor J.D. Eckman, Inc.
Original Contract Value $12,877,625.31
NTP date 12/9/2024
Original Completion Date 11/14/2028
Project Scope This project consists of a bridge replacement on SR 0011 (West King Street) over Norfolk Southern Railroad and other miscellaneous construction, all as
indicated on the approved drawings included in the Bid Package for STATE
ROUTE 0011, SECTION 095, in FRANKLIN COUNTY, SOUTHAMPTON
TOWNSHIP and SHIPPENSBURG BOROUGH, from Segment 0540 Offset
3134 to Segment 0560 Offset 0111, for an overall project length of 1,164
linear feet (0.306 mile).
2
Project Update This contract has a one year waiting period at the beginning to obtain all
required railroad coordination. If all required railroad coordination is
attained prior to the first 365 days, the contractor will be able to begin
work only when authorized in writing by the Department. This one year
waiting period will also be used for utility coordination and relocation.
Utility pole and overhead wire relocations labeled as prior work have not
yet been completed. Utility coordination meetings will begin soon, and we
do not foresee any utility delays at this time. Physical work expected to
start Spring 2026.
Project Description PA997 & SR2015 Intersection
ECMS # 106709
SR-Section 997-037
Contractor Mitchell Knorr dba Mitchell Knorr Contracting
Original Contract Value $6,224,217.92
NTP date 3/3/2025
Original Completion Date 8/22/2028
Project Scope This project is for roadway widening, roundabout construction, ADA curb
ramps, drainage improvements, stormwater management, lighting, and other miscellaneous construction, all as indicated on the approved drawings included
in the Bid Package for STATE ROUTE 0997, SECTION 037, and for STATE
ROUTE 2015, SECTION 009, in FRANKLIN COUNTY, WASHINGTON
TOWNSHIP, from 800' south of SR 2015 (Orchard Road/Tomstown Road) at Segment 0100 Offset 0098 to 1500' north of SR 2015 (Orchard Road/Tomstown Road) at Segment 0110 Offset 0676.
Project Update Let date was January 16, 2025. Pre-construction meeting tentatively
scheduled for February 26th. Physical work expected to start in Spring
2025.