HomeMy WebLinkAboutFranklin MPO TIP Amendment 1HOW TO READ THE TIP MODIFICATION REPORT
The enclosed report identifies specific projects and provides details regarding the
changes in funding that is being proposed on those projects.
The following is an explanation of the items in this report:
•"Project Title" provides the project title as it appears in MPMS
•“MPMS” is the project identification number in the multi-modal project
management system (MPMS).
•“Ph” is the project phases that is being adjusted on that line.
•“Prog" shows whether the funding on that row is indicative of funding levels before
the change, after the change, or as the proposed change.
•"Funds - Fed" indicates the type of federal funding being adjusted on that row.
Funding abbreviations are as follows:
NHPP - National Highway Performance Program
STP - Surface Transportation Program
BRIP - Bridge Improvement Program
BOF - Bridge Off-System
•"Funds - Sta." indicates the type of state funding being adjusted on that row.
Funding abbreviations are as follows:
185 - State Bridge Construction
581 - Highway Construction, State Infrastructure, Etc.
•The next four columns are the dollars as they are or would be programmed on the
TIP for each project sorted by TIP year and source of funding as Federal, State, or
Local.
•"FFY 2029- FFY 2036" indicates funding that is being moved beyond the current 4-
year TIP and is anticipated for programming in future TIP updates.
•"Remarks" provides a brief description for the purpose of the amendment of each
project or project phase
FFY 2025-2028 TIP MODIFICATIONS FORM
Date: 11/14/2024
Page 1 of 1
Project Title MPMS Ph Prog Fed Sta.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.Fed.Sta.Loc.
PA997 & SR2015
Intersection Before HSIP
Before STP
Adjust HSIP
997/037 Adjust STP
After HSIP
Franklin After STP
Highway Reserve Before STP 581
Before NHPP
Adjust STP 581
Adjust NHPP
After STP 581
Franklin After NHPP
Remarks
After FFY Totals
Before FFY Totals
Adjustments
Franklin
This is a reserve line item.
87805 CON
FFY 2027 and FFY 2028 for $2,226,778 for storm
water basin construction, items for NPDES permit,
traffic control, and additional costs for inspection
due to overall project cost increase. This project
consists of installing two roundabouts at the
intersection of PA997 and SR2015 (Tomstown
Road) and the intersection of PA997 and
Washington Township Boulevard in Washington
Township, Franklin County. The estimated let date
of this project is 12/12/2024.
106709 CON1
2
FFY