HomeMy WebLinkAboutSTIP/TIP MOU for 2021-2024Memorandum of Understanding (MOU)
Franklin County Metropolitan Planning Organization (FCMPO)
Procedures for 2021-2024
Transportation Improvement Program (TIP) Revisions
Purpose: This memorandum of understanding (MOU) between the Pennsylvania
Department of Transportation (PennDOT) and the Franklin County Metropolitan
Planning Organization (FCMPO) establishes procedures to be used for
processing revisions to the FY 2021-2024 Transportation Improvement Program.
Definitions:
● Administrative Modification is a minor revision to a Transportation Improvement
Program (TIP). Amendment is a revision to a TIP that involves a major change toa
project included in a TIP.
● Betterment consists of surface treatments/corrections to existing roadway [preferably
within the Pennsylvania Department of Transportation’s (PennDOT’s) right-of-way] to
maintain and bring the infrastructure to current design standards for that classification of
highway. This may involve full depth base repair, shoulder widening, increased lane
widths, correction of super-elevation, as well as, drainage improvements and guide rail
updates.
● Change in Scope is a substantial alteration to the original intent or function of a
programmed project.
● Cooperating Parties include PennDOT, Franklin County MPO, Federal Highway
Administration (FHWA), and Federal Transit Administration (FTA).
● Fiscal Constraint Chart (FCC) is an Excel spreadsheet or a chart generated by the
Multimodal Project Management System (MPMS) that depicts the transfer of funds
● Interstate Management (IM) Program is PennDOT’s four-year listing of statewide
interstate maintenance (non-capacity adding) projects.
● New Project is a project that is not programmed in the current TIP and does not have
previous obligations from a prior TIP.
● Planning Partner is one of the following: MPOs, or RPOs, or the independent County of
Wayne.
● Public Participation Plan (PPP) is a documented broad-based public involvement
process that describes how FCMPO will involve and engage the public in the
transportation planning process to ensure that the concerns of stakeholders are identified
and addressed in the development of transportation plans and programs.
● Rapid Bridge Replacement (RBR) Initiative (developed via a Public Private
Partnership – P3) will follow the Statewide Managed Program guidance in the
administration of the program. For example, the RBR Initiative project rollouts,
1
independent of time intervals, will be considered an amendment on the state’s TIP
(STIP). Placement of RBR projects and or line items on Franklin County’s TIP will be
considered as an administrative action.
● Reserve Line Item holds funds that are not dedicated to a specific project(s) and may be
used to cover cost increases or add a new project or project phase(s).
● Revision is either an Amendment or an Administrative Modification to the TIP.
● Statewide Managed Program (Statewide Program) includes those transportation
improvements or projects that are managed on the STIP, including project selection, at
the PennDOT Central office level, with possible regional Planning Partner input and
solicitation. Examples include but are not limited to Highway Safety Improvement
Program (HSIP), Railroad Crossing Program (RRX), and State Transportation
Alternatives Program (TAP) projects. The Interstate Management Program (IM) will
remain its own individual program.
TIP Administration:
The Federal Highway Administration (FHWA) and the Federal Transit Administration (FTA)
will only authorize projects and approve grants for projects that are programmed in the current
approved TIP. If the MPO or PennDOT wishes to proceed with a federally funded project not
programmed on the TIP, a revision must be made.
The federal statewide and metropolitan planning regulations contained in 23 CFR § 450 govern
the provisions for revisions of the FCMPO TIP. The intent of this federal regulation is to
acknowledge the relative significance, importance, and/or complexity of individual programming
actions. If necessary, 23 CFR § 450.328 permits the use of alternative procedures by the
cooperating parties to effectively manage actions encountered during a given TIP cycle.
Cooperating parties include PennDOT, MPO, FHWA, and FTA. Any alternative procedures
must be agreed upon and documented in the TIP.
TIP revisions must be consistent with Pennsylvania’s Transportation Performance Management
(TPM) requirements, Pennsylvania’s Long-Range Transportation Plan (LRTP), and the MPO’s
LRTP. In addition, TIP revisions must support Pennsylvania’s Transportation Performance
Measures, the Transportation Asset Management Plan (TAMP), the Transit Asset Management
(TAM) Plan, the Strategic Highway Safety Plan (SHSP) and Congestion Management Plan
(CMP), as well as PennDOT’s Connects policy. Over the years, Pennsylvania has utilized a
comprehensive planning and programming process that focuses on collaboration between
PennDOT, FHWA, FTA, and MPOs at the county and regional levels. This approach will be
applied to begin implementation of TPM and Performance Based Planning and Programming
(PBPP). PBPP is PennDOT’s ongoing assessment, target setting, reporting and evaluation of
performance data associated with the TIP investment decisions. This approach ensures that each
2
dollar invested is being directed to meet strategic decisions and enhances the overall
performance of the Commonwealth’s transportation system.
TIP revisions must correspond to the adopted provisions of FCMPO’s Public Participation Plan
(PPP). A PPP is a documented broad-based public involvement process that describes how the
MPO will involve and engage the public in the transportation planning process to ensure that
comments, concerns, or issues of the public and interested parties are identified and addressed in
the development of transportation plans and programs. A reasonable opportunity for public
review and comment shall be provided for significant revisions to the TIP.
All projects within the non-attainment or maintenance area of Franklin County will be screened
for Air Quality significance. PennDOT will coordinate with FCMPO to screen Statewide
Program projects for Air Quality significance. If a revision adds a project, deletes a project, or
impacts the schedule or scope of work of an air quality significant project in a nonattainment or
maintenance area, a new air quality conformity determination will be required, if deemed
appropriate by the PennDOT Air Quality Interagency Consultation Group (ICG). If a new
conformity determination is deemed necessary, an amendment to the FCMPO’s Long Range
Transportation Plan (LRTP) shall also be developed and approved by the MPO. The modified
conformity determination would then be based on the amended LRTP conformity analysis, and
public involvement procedures consistent with the region’s PPP are required.
The federal planning regulations, 23 CFR 450.324(c), define update cycles for FCMPO. If a
FCMPO’s LRTP expires because the LRTP has not been updated in accordance with the
planning cycle defined in the federal planning regulations, then the provisions of this MOU will
not be utilized. During a LRTP expiration, all STIP/TIP revisions that involve projects with
federal funds within FCMPO, where the LRTP expiration occurred, will be treated as an
amendment and require federal approval. There will be no administrative modifications to
projects with any federal funds until the FCMPO LRTP is in compliance with the federal
planning regulations.
TIP Revisions:
In accordance with the federal transportation planning regulations 23 CFR 450 revisions to the
TIP will be handled as an Amendment or an Administrative Modification based on agreed upon
procedures detailed below.
An Amendment is a revision that adds a new project, deletes an existing project, or
involves a major change to an existing project included in the FCMPO’s TIP that:
● Affects air quality conformity regardless of the cost of the project or the funding
source;
3
● Adds a new project, deletes a project that uses federal funds, or federalizes a
project that previously was 100% state and/or locally funded. A new project is a
project that is not programmed in the current TIP, and does not have previous
obligations from a prior TIP. (Federally-funded Statewide Program projects are
excluded from this provision);
● Adds a new phase(s) to an existing project, deletes a project phase(s) or
increases/decreases a project phase(s) that uses federal funds where the revision
exceeds the following thresholds:
○ $2 million (Federally-funded Statewide Program projects are excluded
from this provision)
● Involves a change in the scope of work to a project(s) that would:
○ Result in an air quality conformity re-evaluation;
○ Result in a revised total project estimate that exceeds 50%; or
○ Results in a change in the scope of work on any federally-funded project
that is significant enough to essentially constitute a new project.
Approval by FCMPO is required for Amendments. FCMPO must then initiate PennDOT
Central Office approval using the e-STIP process. An e-STIP submission must include a Fiscal
Constraint Chart (FCC) that clearly summarizes the before, requested adjustments, after changes,
and detailed comments explaining the reason for the adjustment(s), and provides any supporting
information that may have been prepared. The FCC documentation should include any
administrative modification actions that occurred along with or were presented with this action at
the FCMPO meeting. The supporting documentation should include PennDOT Program
Management Committee (PMC) materials, if available.
The initial submission and approval process for the federally-funded Statewide Program or
increases/decreases exceeding the thresholds defined in the STIP MOU will be considered an
amendment to the STIP (subsequent placement of these individual projects or line items on the
MPO TIP will be considered an administrative modification). In the case of Statewide Programs,
including the Interstate Management Program and other federally-funded statewide programs,
approval by the PMC and FHWA is required.
An Administrative Modification is a minor revision to the FCMPO TIP that:
● Any changes to the federally-funded Statewide Program, including any funding
increases/decreases to project phases will be considered an administrative modification
on the FCMPO TIP. In the case of Statewide Programs, including the IM Program and
other federally-funded statewide programs, approval by PennDOT’s PMC and FHWA is
required.
4
● Shifts federally-funded projects, a federally-funded project phase(s), or federal funds to
existing federally-funded projects or a federally-funded project phase(s) in the approved
TIP and must maintain year-to-year TIP fiscal constraint requirements;
● Adds a project from a funding initiative or line item that uses 100 percent state or
non-federal funding, or FCMPO TIP placement of the federally-funded Statewide
Program;
● Adds a project for emergency repairs to a highway, bridge or transit project, except those
involving substantial functional, location, or capacity changes;
● Draws down or returns funding from an existing TIP reserve line item and does not
exceed the thresholds established above. (A reserve line item holds funds that are not
dedicated to a specific project(s) and may be used to cover cost increases or add an
additional project phase(s) to an existing project);
● Adds federal or state capital funds from low-bid savings, de-obligations, release of
encumbrances, or savings on programmed phases to another programmed project phase
or line item and does not exceed the above thresholds;
● Splits a project into two or more separate projects to facilitate project delivery;
● Advances a project phase from the 2nd or 3rd four years of the TYP or FCMPO’s RTP
for a project that has another phase included in the TIP using federal funds;
● Adds, advances, or adjusts federal funding for a project based on FHWA August
Redistribution.
Administrative Modifications do not affect air quality conformity, nor involve a significant
change in the scope of work to a project(s) that would trigger an air quality conformity
re-evaluation; do not add a new federally-funded project or delete a federally funded project; do
not exceed the threshold established in the MOU between PennDOT and FCMPO (as detailed in
the aforementioned Amendment Section); and do not result in a change in scope on any
federally-funded project that is significant enough to essentially constitute a new project. (A
change in scope is a substantial alteration to the original intent or function of a programmed
project.)
Administrative Modifications do not require federal approval. PennDOT and FCMPO will
work cooperatively to address and respond to any FHWA and/or FTA comment(s). FHWA and
FTA reserve the right to question any administrative action that is not consistent with federal
regulations or with this MOU where federal funds are being used.
All revisions, amendments, and administrative modifications shall be identified, numbered, and
grouped as one action on a FCC demonstrating both project and program fiscal constraint. The
identified grouping of projects (the entire revision action) will require review and/or approval by
the cooperating parties. In the case that a project phase is pushed out of the TIP period, FMCPO
5
will demonstrate, through an FCC, fiscal balance of the subject project phase in the second or
third years of the TYP and/or FCMPO.
Financial Constraint:
Demonstration that STIP/TIP fiscal constraint is maintained takes place through a FCC. Real
time versions of the STIP/TIP are available to FHWA and FTA through PennDOT’s Multimodal
Project Management System (MPMS). All revisions must maintain year-to-year fiscal constraint
23 CFR 450.218(l) and 23 CFR 450.326(g)(j)&(k) for each of the four years of the STIP/TIP. All
revisions shall account for year of expenditure (YOE) and maintain the estimated total cost of the
project or project phase within the time-period [i.e., fiscal year(s)] contemplated for completion
of the project, which may extend beyond the four years of the STIP/TIP. The arbitrary reduction
of the overall cost of a project, or project phase(s), shall not be utilized for the advancement of
another project.
Financial Reporting:
PennDOT will provide reports to FCMPO and FHWA no later than 30 days after the end of each
quarter and each Federal Fiscal Year (FFY). At a minimum, this report will include the actual
federal obligations and state encumbrances for highway/bridge projects by FCMPO and
Statewide programs. In addition, PennDOT will provide the Transit Federal Capital Projects
report at the end of each FFY to all of the parties listed above, CAT, and FTA. The reports can
be used by FCMPO as the basis for compiling information to meet the federal annual listing of
obligated projects requirement 23 CFR 450.334. Additional content and any proposed changes to
the report will be agreed upon by PennDOT, FHWA and FTA.
TIP Transportation Performance Management:
In accordance with 23 CFR 450.326(c), PennDOT and FCMPO will ensure TIP revisions
promote progress toward achievement of performance targets.
FCMPO TIP Revision Procedures:
When FCMPO’s TIP is adopted, a copy of this MOU will be included with the TIP
documentation to clarify how FCMPO will address all TIP revisions. FCMPO revision
procedures are developed under the guidance umbrella of the PennDOT-FHWA-FTA MOU. If
FCMPO elects to set more stringent procedures, then PennDOT, FHWA and FTA will adhere to
those more restrictive procedures.
This document will serve as the basis for PennDOT when addressing federally funded FCMPO
TIP revisions.
6
This Memorandum of Understanding will begin October 1, 2020, and remain in effect until
September 30, 2022, unless revised or terminated. Furthermore, it is agreed that this MOU will
be reaffirmed every two years.
We, the undersigned, hereby agree to the above procedures and principles:
Samuel Cressler Jul 20, 2020
Sam Cressler Date
MPO Chairman
Jul 20, 2020
David Keller Date
Commissioner Chairman
Larry Shifflet, Deputy Secretary for Planning Date
Pennsylvania Department of Transportation
July 20, 2020